Billings Water Treatment Plant

Expectations were high when waterworks engineers began their search for protective coatings for eight freshwater filter basins for the City of Billings Water Treatment Plant expansion project. “They wanted a bulletproof system with zero leakage and very good life cycle costs,” according to Tnemec coating consultant Mike Cox. “We needed coatings whose applications were not limited by low substrate temperatures.”

After reviewing some optional coating systems, Cox specified a system including Series 218 MortarClad, an epoxy modified cementitious resurfacer; Series 1 Omnithane, a moisture-cured MIO-zinc urethane primer; and Series 400 ElastoShield, a polyurea elastomer finish coat.

Phase I of the project involved coating four new filter basins constructed of poured-in-place concrete. “The contractor began with an abrasive brush blast of the new concrete. We then addressed the bug holes and voids with the resurfacer, which was applied with masonry floats and trowels,” Cox recalled. “Then the polyurethane primer was rolled on and the finish coat was spray-applied with heated plural component equipment.”

The project’s second phase involves refurbishment of the four old filter basins. The same coating system was specified and is scheduled to begin during late fall 2006 and early winter 2007 when temperatures are normally near freezing. “These older basins were in need of extensive surface prep,” Cox noted. “They had a lot of wear on them and existing coatings that were in the process of failing. All of that had to be removed before using the filler material to resurface the concrete,” Cox acknowledged.

One additional challenge of this project was that the older filter basins were still in service during construction of the expansion, and leakage from the older filter basins was apparent during work on Phase I. “One long wall was shared between the old and new basins,” Cox explained. “And because the coatings on the old basins were failing, we had one area with leakage that we had to work around. That’s why the plant’s engineers wanted to make sure the new coatings would perform.”

“In the end, the owner, engineer and contractors were very impressed with the performance of our system,” Cox added.

    Project Information

    Location
    Billings, Montana

    Owner
    City of Billings

    Completion
    June 2006

    A/E Firm
    HDR, Missoula, Montana

    Field Applicator
    Quality Maintenance Contractors, Muskegon, Michigan

    Printer Friendly Version

    City of Billings Water Treatment Plant

    Contact Your Rep

    Looking for Some Local Coatings Guidance?

    Reach out to one of our knowledgable and reliable representatives near you.

    How to Purchase

    Ready to Order Tnemec?

    We're ready to help. Click below to learn more about our purchasing process.

    Color Requests

    Searching for the Right Color?

    Use our color tool or request more tools from your local representative.

    Continue Exploring in the color tool

    Close

    Color Swatch packet

    When you finish selecting, request your Swatch Packet below. Expect your swatch cards in 5-7 business days. Contact your expert Sales Rep at any time.

    Sorry, there is a maximum of 6 color swatches.

    Request swatch packet

    Continue Exploring in the color tool

    Close